If you are planning building work to a commercial or residential property in England or Wales, there is a good chance the Party Wall etc. Act 1996 applies. Before certain works can start, the building owner must serve a party wall notice on each affected neighbour, known in the Act as the adjoining owner. Getting the notice right, and serving it in good time, is one of the easiest ways to keep a project on programme.

This guide explains the three main types of party wall notice, how much notice each one needs, what a notice should include and how adjoining owners can respond. It is general guidance rather than legal advice, and every project depends on its own facts.

What is a party wall notice?

A party wall notice is a formal written notice that tells an adjoining owner about work covered by the Act. It gives them the chance to consent, or to dissent so that a surveyor can settle the details in a party wall award before work begins. The building owner is the person or organisation carrying out the work. An adjoining owner can include a freeholder and, in many cases, a leaseholder or tenant with a sufficient interest in the neighbouring property, so commercial landlords and tenants can both be involved.

The three main types of party wall notice

1. Line of junction notice (section 1)

This applies where you want to build a new wall on or right up to the boundary line between two properties, where there is currently no building on the line other than a boundary wall. Typical examples are a new extension or industrial unit built up to the boundary. Under section 1, the notice must be served at least one month before the intended start date and must describe the intended wall.

2. Party structure notice (section 3)

This covers work to an existing party wall, party fence wall or other party structure under section 2 of the Act. Common examples include cutting into a party wall to insert steel beams, raising or thickening a wall, underpinning a party wall, removing chimney breasts that are attached to it, and cutting away projections. A party structure notice must be served at least two months before the work is due to begin. It must state the building owner’s name and address, the nature and particulars of the proposed work and the date it will begin. Where special foundations are proposed, it must also include plans, sections and construction details with particulars of the loads.

3. Notice of adjacent excavation (section 6)

This is often the notice that catches commercial projects out. Section 6 applies where you plan to excavate, or excavate for and erect a building or structure:

  • within 3 metres of a neighbouring building or structure, where any part of the excavation will go deeper than the bottom of the neighbour’s foundations, or
  • within 6 metres of a neighbouring building or structure, where the excavation will cut a line drawn downwards at 45 degrees from the bottom of the neighbour’s foundations.

The notice must be served at least one month before excavation starts. It must say whether you propose to underpin or otherwise strengthen or safeguard the neighbour’s foundations, and it must be accompanied by plans and sections showing the site and depth of the excavation and, where relevant, the site of any new building or structure.

Party wall notice periods at a glance

  • Line of junction notice: at least one month before work starts.
  • Party structure notice: at least two months before work starts.
  • Adjacent excavation notice: at least one month before excavation starts.
  • Response period: the adjoining owner has 14 days from service to give written consent.
  • Validity: party structure and excavation notices generally cease to have effect if the work has not begun within 12 months of service and is not carried on with due diligence.

Work can start earlier than the notice period where the adjoining owners and occupiers agree in writing. On larger schemes, though, it is wise to build the full notice period, plus time for surveyors to agree an award, into the programme from the outset.

Get a quote for your party wall survey in less than 60 seconds.

Simply enter your requirements into our online quote calculator.

GET A QUOTE FOR YOUR SURVEY

GET STARTED

0$
Crunching the numbers...
Get your instant survey quote

What type of survey or report do you require?

You need to select an item to continue
Almost there...

Please enter the location details of the property you'd like surveyed.

For Employer's Agent please enter the project location.

You need to select an item to continue
Property Location
You need to select an item to continue
Pop in your survey details...

Please enter the size of the property you would like surveyed.

You need to select an item to continue
Pop in your survey details...

Please enter the size of the property you would like surveyed.

You need to select an item to continue
Pop in your survey details...

Please enter the size of the property you would like surveyed.

You need to select an item to continue
Pop in your survey details...

Please enter the size of the property you would like surveyed.

You need to select an item to continue
Pop in your survey details...

Please enter the size of the property you would like surveyed.

You need to select an item to continue
Pop in the details of your home..
You need to select an item to continue
Pop in your survey details...
You need to select an item to continue
Pop in your survey details...

Please enter the value of the project you require an Employer's Agent for.

You need to select an item to continue
Pop in your survey details...

Please enter the size of the property you would like surveyed.

You need to select an item to continue
Pop in your survey details...

Please enter the size of the property you would like surveyed.

You need to select an item to continue
Hurrah! You're done.

Fill in your details below to get your instant quote.

Fill in your details below to get your instant quote.

By clicking below you are agreeing to our Privacy Policy.

Summary

DescriptionInformationQuantityPrice
Discount :
Total :

How can an adjoining owner respond?

Once a notice is served, the adjoining owner usually has three options:

  1. Consent in writing. The work can then go ahead under the notice without a surveyor being appointed. Many building owners still offer a schedule of condition of the neighbouring property first, so there is a clear record if damage is alleged later.
  2. Dissent and agree to one surveyor. Both owners appoint a single agreed surveyor to act impartially and prepare the party wall award.
  3. Dissent and appoint their own surveyor. Each owner appoints a surveyor, and the two surveyors select a third surveyor who can be called on if they cannot agree.

If the adjoining owner does not reply with written consent within 14 days, they are treated as having dissented and a dispute is deemed to have arisen. A dispute in this sense is simply the trigger for the surveyor process. It does not mean the neighbours have fallen out. If an adjoining owner then refuses or fails to appoint a surveyor within 10 days of being formally asked, the building owner can appoint one on their behalf.

For party structure notices, the adjoining owner can also serve a counter notice within one month, asking for additional works for their own benefit, such as piers, recesses or deeper special foundations, which they may have to pay for.

What happens after a dispute arises?

The appointed surveyor or surveyors will review the proposals, inspect the adjoining property and agree a party wall award. The award sets out what work can be done, how and when it can be done, and who pays for it. It will normally include a schedule of condition of the neighbouring property. You can read more about this stage in our guide to the process for agreeing a party wall award and in what is included in a party wall award. As a general rule, the building owner pays the reasonable costs of the surveyors.

Common party wall notice mistakes

  • Serving too late. A two-month notice served a few weeks before the contractor arrives can delay the start date.
  • Missing an adjoining owner. On commercial sites there may be a freeholder, a head leaseholder and occupying tenants. A Land Registry search helps to identify everyone with an interest.
  • Using the wrong notice. One project can need several notices, for example a party structure notice for steel beams and an excavation notice for new foundations.
  • Leaving out key information. An excavation notice without plans and sections, or a party structure notice without a start date, may not be valid.
  • Starting work without notice. This can lead to an injunction stopping work and to claims for damage, and it makes it harder to show what condition the neighbouring property was in beforehand.

Party wall notice FAQs

Do I need a party wall notice for an office or shop fit-out?

Not always. Minor works such as fixing shelving, light fittings or replastering usually fall outside the Act. Cutting into a party wall to take a beam, removing a chimney breast or digging new foundations close to a neighbour normally needs notice. A surveyor can confirm which works are notifiable.

Can I serve a party wall notice myself?

Yes. The Act does not require a surveyor to serve notices, but many building owners use one to make sure each notice is the right type, includes the right information and is served on the right people.

Does planning permission or Building Regulations approval replace a party wall notice?

No. The Party Wall Act is separate from planning permission and Building Regulations. You may need all three for the same project.

Get help with party wall notices

Whether you are a building owner planning works or an adjoining owner who has just received a notice, an experienced party wall surveyor can help you serve or respond to notices correctly and agree an award without unnecessary delay. We can match you with surveyors in London, Birmingham, Manchester and Bristol. Get your quote in under 60 seconds.